May 31st I went to Rosenzweig in the Bronx and purchased some lumber, poplar, pine
June 3rd, From the Heavy Construction lumber yard, got some 8×8, 4×4, 2×4, 2×8, 2×10 construction lumber
June 4th ~ 20th, Milling work and making some strips of 2", 2.5", 3", 3.5" 4.5", 5", approximately about 100 pieces
for each sizes.
June 21st, Coloring or water sealing work for all the lumber
June 22nd, Delivered all the materials to the site
June 23rd, First day to start to making the installation
July 2nd, Completed the installation