Purchasing lumber and the processing

May 31st I went to Rosenzweig in the Bronx and purchased some lumber, poplar, pine

June 3rd, From the Heavy Construction lumber yard, got some 8×8, 4×4, 2×4, 2×8, 2×10 construction lumber

June 4th ~ 20th, Milling work and making some strips of 2", 2.5", 3", 3.5" 4.5", 5", approximately about 100 pieces

                          for each sizes.

June 21st, Coloring or water sealing work for all the lumber

June 22nd, Delivered all the materials to the site

June 23rd, First day to start to making the installation

July 2nd,   Completed the installation